Skip to main content
← Back

Purti Apartments Condominium, Erandwane

by Vyas Buildcon Private Limited. Erandwane, Pune 411004. View on Google Maps

Launched
2 years 7 months promised
Possession date (MahaRERA)
1 year 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
1 of 147% booked

Project facts

3 BHK14
Total units14
Buildings1
Land0.1 acres
Landowner share2
Rehab units5
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: total units 5 → 14

Share on WhatsApp

Compared with 6 similar projects in PIN 411004

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411004
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 7 mths2 yrs 6 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)June 2028December 2028
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
11 months of the promised 2 years 7 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 60%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 60%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
60%0%0%1
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Purti Apartments Condominium (MahaRERA PR1260002501388) is a residential project by Vyas Buildcon Private Limited in Erandwane, Pune 411004. It was launched in November 2025. It has 14 units in 1 building, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation 60% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

1 of its 14 units is booked (7%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1260002501388.Check it on MahaRERA (PR1260002501388)All projects in Deccan