Skip to main content
← Back

Icon, Darumbare

by Evita Krisala Township LLP. Darumbare, Pune 410506. View on Google Maps

Launched
4 years 11 months promised
Possession date (MahaRERA)
4 years 7 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 3 buildings
Units booked
Bookings not reported

Project facts

2 BHK16
3 BHK115
4 BHK113
Total units244
Buildings3
Land3.4 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 months of the promised 4 years 11 months have passed
Concrete structure (RCC) 0% complete

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Icon (MahaRERA PR1260002600818) is a residential project by Evita Krisala Township LLP in Darumbare, Pune 410506. It was launched in June 2026, which makes it one of the newest launches in Talegaon Dabhade, Darumbare. It has 244 units in 3 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is May 2031, unchanged since launch. Construction, averaged across its 3 buildings: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet.

Krisala's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA32
Completed without extending the possession date13
Completed after an extension, or lapsed4
Under construction15
Possession date extended by the builder4
Typical time from launch to 100% structure3 years 8 months
Complaints on MahaRERA, all Krisala projects99 (12 of 32 projects)

See all Krisala projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1260002600818.Check it on MahaRERA (PR1260002600818)All projects in Talegaon Dabhade, Darumbare