by Shivsamarth Developers · Kirkatwadi, Pune 411024 · Map

Launched
Jul 20264 yrs 5 mths originally promised
Possession (MahaRERA)
Apr 2031Extended by 4 mths
Concrete structure
0%Average of 2 towers
Booked
28 of 7239%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
63
3 BHK
9
Total units
72
Buildings
2
Land
1 acre
Phases
1
MahaRERA complaints
0

Construction progress

From the architect's Form 1 filed with MahaRERA, latest filing Oct 2026. The last 4 updates per tower.

Last 4 updates, tower by tower
Wing A
UpdateExcavationStructureFinishes
Oct 202670%0%0%
Wing B
UpdateExcavationStructureFinishes
Oct 202670%0%0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%0%0%28

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹3.6 crore spent · latest estimate ₹23.5 crore · Oct 2026

Latest estimate ₹23.5 croreOct 2026: ₹3.6 crore3.6Oct 2026
₹ crore spent
Spent at each update
UpdateSpent
Oct 2026₹3.6 crore

Compared with 3 similar projects in PIN 411024

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411024
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 5 mths4 yrs 5 mths
Possession date extendedBy 4 mths2 of 3
Possession date (MahaRERA)Apr 2031Apr 2031
Concrete structure (RCC)0%0%
Units booked39%18%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Sylvora by Shivsamarth Developers is a 72-unit project in Kirkatwadi, Pune 411024, launched in July 2026 with possession due in April 2031. 28 units booked out of total 72 units. Work on the concrete structure (RCC) has not started.

Read full summary

Sylvora is a project by Shivsamarth Developers in Kirkatwadi, Pune 411024, registered with MahaRERA as PR1260002601363. It was launched in July 2026. It has 72 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2031, extended by 4 months from the original December 2030. Construction, averaged across its 2 towers: excavation 70% complete, structure (RCC) not started, final finishes not started.

28 units booked out of total 72 units (39%).