Kunal Manthan, Rahatani

by Kunal Landmarks · Rahatani, Pune 411017 · Map

Launched
Aug 20263 yrs 4 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked
4 of 597%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
42
3 BHK
16
Total units
59
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
0

Construction progress by tower

From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.

Last 4 updates
Building
UpdateExcavationStructureFinishes
Oct 202630%0%0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
30%0%0%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹42 lakh spent · latest estimate ₹18.4 crore · Oct 2026

Latest estimate ₹18.4 croreOct 2026: ₹42 lakh0.4Oct 2026
₹ crore spent
Spent at each update
UpdateSpent
Oct 2026₹42 lakh

Compared with 4 similar projects in PIN 411017

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411017
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths3 yrs 10 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2029Jun 2030
Concrete structure (RCC)0%0%
Units booked7%48%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Kunal Manthan by Kunal Landmarks is a 59-unit project in Rahatani, Pune 411017, launched in August 2026 with possession due in December 2029. 4 units booked out of total 59 units. Work on the concrete structure (RCC) has not started.

Read full summary

Kunal Manthan is a project by Kunal Landmarks in Rahatani, Pune 411017, registered with MahaRERA as PR1260002601428. It was launched in August 2026. It has 59 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 30% complete, structure (RCC) not started, final finishes not started.

4 units booked out of total 59 units (7%).