Backwaters, Bhugaon

by Richland Hospitality LLP · Bhugaon, Pune 412115 · Map

Launched
Aug 20263 yrs 4 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
9%Mid-construction
Booked
0 of 1270%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
23
2 BHK
104
Total units
127
Buildings
1
Land
31.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation30%
Concrete structure (slabs)9%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
30%9%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 412115

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412115
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths4 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2029Nov 2030
Concrete structure (RCC)9%0%
Units booked0%2%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Backwaters by Richland Hospitality LLP is a 127-unit project in Bhugaon, Pune 412115, launched in August 2026 with possession due in December 2029. 0 units booked out of total 127 units. The concrete structure (RCC) is 9% complete.

Read full summary

Backwaters is a project by Richland Hospitality LLP in Bhugaon, Pune 412115, registered with MahaRERA as PR1260002601514. It was launched in August 2026. It has 127 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 30% complete, structure (RCC) 9% complete, final finishes not started.

0 units booked out of total 127 units (0%).