Harmony Heights, Vadgaon Sheri

Ready to move

by Bramhacorp Limited · Vadgaon Sheri, Pune 411014 · Map

Launched
Sep 20268 mths promised
Possession (MahaRERA)
May 2027Not extended
Concrete structure
100%Ready to move
Booked
0 of 610%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
22
1 BHK
26
2 BHK
13
Total units
61
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress by tower

From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.

Last 4 updates
Building
UpdateStructureFinishes
Oct 2026100%100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹1.0 crore spent · latest estimate ₹5.0 crore · Oct 2026

Latest estimate ₹5.0 croreOct 2026: ₹1.0 crore1Oct 2026
₹ crore spent
Spent at each update
UpdateSpent
Oct 2026₹1.0 crore

Compared with 3 similar projects in PIN 411014

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411014
MeasureThis projectSimilar projects
Launch to possession (as first promised)8 mths5 yrs 4 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)May 2027Dec 2031
Concrete structure (RCC)100%0%
Units booked0%8%
MahaRERA complaints (filed by or against the builder)00

The 3 projects, latest price per sq ft

Other phases of this project are not included in the similar projects.

About this project

Harmony Heights by Bramhacorp Limited is a 61-unit project in Vadgaon Sheri, Pune 411014, launched in September 2026 with possession due in May 2027. 0 units booked out of total 61 units. The concrete structure (RCC) is complete.

Read full summary

Harmony Heights is a project by Bramhacorp Limited in Vadgaon Sheri, Pune 411014, registered with MahaRERA as PR1260002601901. It was launched in September 2026. It has 61 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is May 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

0 units booked out of total 61 units (0%).

Bramhacorp's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA32
Total units across these projects6,462
Completed without extending the possession date10
Completed after an extension0
Lapsed3
Under construction18
Not updated on MahaRERA for over a year1
Possession date extended on the builder's application1
Typical time from launch to 100% structure3 years 2 months
MahaRERA complaints (filed by or against the builder), all Bramhacorp projects12 (11 of 32 projects)