Skip to main content
← Back

Dreams A Wing, Varale

by Dhanayogam Housing & Infrastructure Private Limited. Varale, Pune 410507. View on Google Maps

Launched
3 years 10 months promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
10%Mid-construction
Units booked
Bookings not reported

Project facts

1 BHK19
2 BHK13
Total units32
Buildings1
Land0.5 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 5 similar projects in PIN 410507

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 410507
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 10 mths2 yrs 11 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)December 2029December 2028
Concrete structure (RCC) complete10%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
8 months of the promised 3 years 10 months have passed
Concrete structure (RCC) 10% complete

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Dreams A Wing (MahaRERA PR1261012502460) is a residential project by Dhanayogam Housing & Infrastructure Private Limited in Varale, Pune 410507. It was launched in February 2026, which makes it one of the newest launches in Talegaon Dabhade, Darumbare. It has 32 units in 1 building, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 10% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1261012502460.Check it on MahaRERA (PR1261012502460)All projects in Talegaon Dabhade, Darumbare