Skip to main content
← Back

My Home Sanctuary Phase I, Mamurdi

by Mamurdi Developers LLP. Mamurdi, Pune 412101. View on Google Maps

Launched
5 years 9 months promised
Possession date (MahaRERA)
5 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 6 buildings
Units booked
Bookings not reported

Project facts

1 BHK104
2 BHK375
3 BHK187
Other units (shops, offices or not given by type)38
Total units704
Buildings6
Land9.9 acres
Reserved units106
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
7 months of the promised 5 years 9 months have passed
Concrete structure (RCC) 0% complete

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

My Home Sanctuary Phase I (MahaRERA PR1261012502725) is a residential project by Mamurdi Developers LLP in Mamurdi, Pune 412101. It was launched in March 2026, which makes it one of the newest launches in Kiwale, Ravet, Dehu Road. It has 704 units in 6 buildings: 666 homes (1, 2 & 3 BHK) and 38 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2031, unchanged since launch. Construction, averaged across its 6 buildings: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1261012502725.Check it on MahaRERA (PR1261012502725)All projects in Kiwale, Ravet