Magnus Ab, Pimple Saudagar
by Aswani Realty Nexus LLP · Pimple Saudagar, Pune 411027 · Map
- Launched
- Aug 20264 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2030Not extended
- Concrete structure
- 0%Average of 2 towers
- Booked
- 0 of 1090%
- Price per sq ft
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 48
- 4 BHK
- 61
- Total units
- 109
- Buildings
- 2
- Land
- 4.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
From the architect's Form 1 filed with MahaRERA, latest filing Oct 2026. The last 4 updates per tower.
Last 4 updates, tower by tower
| Update | Structure | Finishes |
|---|---|---|
| Oct 2026 | 0% | 0% |
| Update | Structure | Finishes |
|---|---|---|
| Oct 2026 | 0% | 0% |
Excavation is 100% in every tower.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹31.0 crore spent · latest estimate ₹62.6 crore · Oct 2026
Spent at each update
| Update | Spent |
|---|---|
| Oct 2026 | ₹31.0 crore |
About this project
Magnus Ab by Aswani Realty Nexus LLP is a 109-unit project in Pimple Saudagar, Pune 411027, launched in August 2026 with possession due in December 2030. 0 units booked out of total 109 units. Work on the concrete structure (RCC) has not started.
Read full summary
Magnus Ab is a project by Aswani Realty Nexus LLP in Pimple Saudagar, Pune 411027, registered with MahaRERA as PR1261012601712. It was launched in August 2026. It has 109 units in 2 buildings, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2030, unchanged since launch. Construction, averaged across its 2 towers: excavation complete, structure (RCC) not started, final finishes not started.
0 units booked out of total 109 units (0%).