Skip to main content
← Back

Yashraj Nakshatra Phase 4, Hadapsar

by Vishwas Developers and Builders. Hadapsar, Pune 411028. View on Google Maps

Launched
10 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
43%Mid-construction
Units booked
Bookings not reported

Project facts

2 BHK24
Total units24
Buildings1
Land1.8 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
8 months of the promised 10 months have passed
Concrete structure (RCC) 43% complete

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%43%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Yashraj Nakshatra Phase 4 (MahaRERA PR1263032502451) is a residential project by Vishwas Developers and Builders in Hadapsar, Pune 411028. It was launched in February 2026, which makes it one of the newest launches in Hadapsar, Handewadi. It has 24 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation 80% complete, structure (RCC) 43% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1263032502451.Check it on MahaRERA (PR1263032502451)All projects in Hadapsar, Handewadi