Veena projects in Mumbai

MahaRERA projects by Veena registered 2017–2026 in Mumbai.

Projects registered with MahaRERA15
Total units across these projects2,186
Full record

MahaRERA projects registered 2017–2026 in Mumbai

Completed without extending the possession date6
Completed after an extension2
Lapsed1
Under construction6
Possession date extended on the builder's application4
Typical time from launch to 100% structure4 years 2 months
MahaRERA complaints (filed by or against the builder), all Veena projects19 (7 of 15 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Chembur (3) · Borivali West (3) · Kandivali West (2) · Jogeshwari West (2) · Santacruz West (1) · Andheri East (1) · Malad West (1)

Under construction

ProjectVillageStagePossessionBooked
Veena BlissKandivali WestEarly stageDecember 20310 units booked out of 30 units for sale
Veena CelestiaBorivali WestEarly stageDecember 20300 units booked out of 44 units for sale
Veena ImperiaJogeshwari WestEarly stageDecember 20302 units booked out of 92 units for sale
Veena InsigniaJogeshwari WestMid-constructionMarch 203046 units booked out of 133 units for sale
Veena Smart Homes · 3 phasesKandivali WestNearing possessionDec 2026468 units booked out of total 503 units
Veena SynergyAndheri EastNearing possessionDecember 2026171 units booked out of total 171 units
Completed
ProjectVillageStatus
Veena SantoorBorivali WestCompleted
Veena SenterioChemburCompleted
Veena SerenityChemburCompleted
Veena SignatureBorivali WestCompleted
Veena SolaceSantacruz WestCompleted
Veena SuyogMalad WestCompleted
Lapsed
ProjectVillageStatus
Veena Serene-ResidentialChemburLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us