Veena Smart Homes, Kandivali West

by V.D. Infratech Private Limited · Kandivali West, Mumbai 400067 · Map

Launched
May 2021First of 3 phases
Possession (MahaRERA)
Dec 2026Extended in all 3 phases
Concrete structure
100%Weighted across 3 phases
Booked
468 of 50393%
Buildings
51.4 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
214
2 BHK
249
Other units
40
Total units
503
Buildings
5
Land
1.4 acres
Phases
3
MahaRERA complaints
2

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Veena Smart Homes
Completed
P51800029400169100%99%
Veena Smart Homes
Completed
P51800031045146100%90%
Veena Smart Homes
Ready to move
P51800032966148100%90%
Show updates by phase

Veena Smart Homes (P51800029400)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%174
100%100%10%–
100%100%10%–
100%100%10%174

"–" means MahaRERA shows no figure for that update.

Veena Smart Homes (P51800031045)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%140
100%100%0%–
100%100%0%–
100%100%0%143

"–" means MahaRERA shows no figure for that update.

Veena Smart Homes (P51800032966)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%154
100%100%90%150
100%30%0%149
100%30%0%90

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services36%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 78%Dec 2025: Concrete structure (RCC) 78%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 4%Dec 2025: Final finishes 4%Jul 2026: Final finishes 32%Oct 2026: Final finishes 36%Excavation 100%Concrete structure (RCC) 100%Final finishes 36%

How to read construction stages

Compared with 4 similar projects in PIN 400067

Projects with 200–1,000 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths4 yrs 4 mths
Possession date extendedYes2 of 4
Possession date (MahaRERA)Dec 2026Mar 2027
Concrete structure (RCC)100%100%
MahaRERA complaints (filed by or against the builder)22

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Veena Smart Homes by V.D. Infratech Private Limited (Veena) is a 503-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, registered with MahaRERA in 3 phases, with possession due in December 2026. 468 units booked out of total 503 units. The concrete structure (RCC) is complete.

Read full summary

Veena Smart Homes is an SRA-sanctioned project by V.D. Infratech Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as 3 phases (P51800029400, P51800031045, P51800032966). The first phase was launched in May 2021. Together the phases have 503 units in 5 buildings: 463 homes (1 and 2 BHK) and 40 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 2 are completed and 1 is active.

The registered possession date is December 2026; all 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 36% complete. All 3 phases have their structure complete.

468 units booked out of total 503 units (93%).

Veena's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA15
Total units across these projects2,186
Completed without extending the possession date6
Completed after an extension2
Lapsed1
Under construction6
Possession date extended on the builder's application4
Typical time from launch to 100% structure4 years 2 months
MahaRERA complaints (filed by or against the builder), all Veena projects19 (7 of 15 projects)

See all Veena projects →