Sakshat Navkar, Borivali West
Ready to moveLapsed
by Navkar Infra Projects · Borivali West, Mumbai 400092 · Map
- Launched
- Jul 20172 yrs 2 mths originally promised
- Possession (MahaRERA)
- May 2025Extended by 5 yrs 8 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 25 of 2793%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 5
- 2 BHK
- 7
- 3 BHK
- 2
- Other units
- 13
- Total units
- 27
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 25 | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 25 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400092
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 2 mths | 2 yrs 6 mths |
| Possession date extended | By 5 yrs 8 mths | 1 of 3 |
| Possession date (MahaRERA) | May 2025 | Feb 2020 |
| Concrete structure (RCC) | 100% | 40% |
| Units booked | 93% | 93% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Ankit Chs, Borivali West
- Rite Aspire, Borivali West
- Dahisar Snehal Chs, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ankit Chs | August 2017 | December 2019 | 40% | 5 units booked out of total 11 units |
| Rite Aspire | August 2017 | December 2023 | 100% | 26 units booked out of total 27 units |
| Dahisar Snehal Chs | August 2017 | February 2020 | 25% | 13 units booked out of total 14 units |
About this project
Sakshat Navkar by Navkar Infra Projects is a 27-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in July 2017; its MahaRERA registration has lapsed. 25 units booked out of total 27 units. The concrete structure (RCC) is complete.
Read full summary
Sakshat Navkar is a BMC-sanctioned project by Navkar Infra Projects in Borivali West, Mumbai 400092, registered with MahaRERA as P51800000503. It was launched in July 2017. It has 27 units in 1 building: 14 homes (1, 2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in May 2025, after an extension of 5 years 8 months from the original September 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
25 units booked out of total 27 units (93%).