- Launched
- Aug 20173 yrs 10 mths originally promised
- Possession (MahaRERA)
- Dec 2023Extended by 2 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 26 of 2796%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 7
- 3 BHK
- 2
- 4 BHK
- 2
- Other units
- 16
- Total units
- 27
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 26 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 26 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400092
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 2 yrs 6 mths |
| Possession date extended | By 2 yrs 6 mths | 3 of 5 |
| Possession date (MahaRERA) | Dec 2023 | Dec 2024 |
| Concrete structure (RCC) | 100% | 25% |
| Units booked | 96% | 45% |
| MahaRERA complaints (filed by or against the builder) | 0 | 2 |
The 5 projects
- Ankit Chs, Borivali West
- Nutan Dream, Borivali West
- Dahisar Snehal Chs, Borivali West
- Madhav Baug, Borivali West
- Sakshat Navkar, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ankit Chs | August 2017 | December 2019 | 40% | 5 units booked out of total 11 units |
| Nutan Dream | August 2017 | December 2024 | 15% | 3 units booked out of total 36 units |
| Dahisar Snehal Chs | August 2017 | February 2020 | 25% | 13 units booked out of total 14 units |
| Madhav Baug | August 2017 | December 2029 | 0% | 0 units booked out of total 73 units |
| Sakshat Navkar | July 2017 | May 2025 | 100% | 25 units booked out of total 27 units |
About this project
Rite Aspire by Rite Developers Pvt Ltd is a 27-unit project in Borivali West, Mumbai 400092, launched in August 2017; its MahaRERA registration has lapsed. 26 units booked out of total 27 units. The concrete structure (RCC) is complete.
Read full summary
Rite Aspire is a project by Rite Developers Pvt Ltd in Borivali West, Mumbai 400092, registered with MahaRERA as P51800009215. It was launched in August 2017. It has 27 units in 1 building: 11 homes (2, 3 and 4 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023, after an extension of 2 years 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.
26 units booked out of total 27 units (96%).