Rite Aspire, Borivali West

Lapsed

by Rite Developers Pvt Ltd · Borivali West, Mumbai 400092 · Map

Launched
Aug 20173 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2023Extended by 2 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
26 of 2796%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
7
3 BHK
2
4 BHK
2
Other units
16
Total units
27
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%26
100%100%0%–
100%100%0%–
100%100%0%26

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400092

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths2 yrs 6 mths
Possession date extendedBy 2 yrs 6 mths3 of 5
Possession date (MahaRERA)Dec 2023Dec 2024
Concrete structure (RCC)100%25%
Units booked96%45%
MahaRERA complaints (filed by or against the builder)02

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Rite Aspire by Rite Developers Pvt Ltd is a 27-unit project in Borivali West, Mumbai 400092, launched in August 2017; its MahaRERA registration has lapsed. 26 units booked out of total 27 units. The concrete structure (RCC) is complete.

Read full summary

Rite Aspire is a project by Rite Developers Pvt Ltd in Borivali West, Mumbai 400092, registered with MahaRERA as P51800009215. It was launched in August 2017. It has 27 units in 1 building: 11 homes (2, 3 and 4 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023, after an extension of 2 years 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.

26 units booked out of total 27 units (96%).