Navkar Paradise, Borivali West

Ready to moveLapsed

by Navkar Infra Projects · Borivali West, Mumbai 400092 · Map

Launched
Jul 20173 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2022Extended by 1 yr 6 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
94 of 9896%
Buildings
21.1 acres
MahaRERA complaints
7Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
26
3 BHK
48
Other units
24
Total units
98
Buildings
2
Land
1.1 acres
Phases
1
MahaRERA complaints
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services99%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 99%Dec 2025: Final finishes 99%Jul 2026: Final finishes 99%Oct 2026: Final finishes 99%Excavation 100%Concrete structure (RCC) 100%Final finishes 99%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%94
100%100%99%–
100%100%99%–
100%100%99%94

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths3 yrs 3 mths
Possession date extendedBy 1 yr 6 mths4 of 6
Possession date (MahaRERA)Dec 2022May 2027
Concrete structure (RCC)100%67%
Units booked96%83%
MahaRERA complaints (filed by or against the builder)72

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Navkar Paradise by Navkar Infra Projects is a 98-unit project in Borivali West, Mumbai 400092, launched in July 2017; its MahaRERA registration has lapsed. 94 units booked out of total 98 units. The concrete structure (RCC) is complete.

Read full summary

Navkar Paradise is a project by Navkar Infra Projects in Borivali West, Mumbai 400092, registered with MahaRERA as P51800000715. It was launched in July 2017. It has 98 units in 2 buildings: 74 homes (2 and 3 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2022, after an extension of 1 year 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

94 units booked out of total 98 units (96%).