Laxmi Narayan Mansion, Borivali West
Lapsed
by Atharva Developers · Borivali West, Mumbai 400092 · Map
- Launched
- Jul 20174 yrs 6 mths promised
- Possession (MahaRERA)
- Jan 2022Not extendedWhat does Lapsed mean?
- Concrete structure
- 74%Mid-construction
- Booked
- –
- Buildings
- 10.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 1
- 3 BHK
- 42
- 4 BHK
- 2
- Other units
- 3
- Total units
- 48
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 74% | 5% | – | |
| 100% | 74% | 5% | – | |
| 100% | 74% | 5% | 19 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400092
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 6 mths | 2 yrs 10 mths |
| Possession date extended | No | 4 of 4 |
| Possession date (MahaRERA) | Jan 2022 | Aug 2027 |
| Concrete structure (RCC) | 74% | 84% |
| Units booked | – | 63% |
| MahaRERA complaints (filed by or against the builder) | 1 | 3 |
The 4 projects
- Navkar Paradise, Borivali West
- Nirdhar Co Operative Housing Society Limited, Borivali West
- Vilas Vaibhav Chs, Borivali West
- Soni Arcade, Building No 2, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Navkar Paradise | July 2017 | December 2022 | 100% | 94 units booked out of total 98 units |
| Nirdhar Co Operative Housing Society Limited | September 2017 | January 2028 | 20% | 16 units booked out of 37 units for sale |
| Vilas Vaibhav Chs | September 2017 | December 2027 | 69% | 4 units booked out of 15 units for sale |
| Soni Arcade, Building No 2 | September 2017 | April 2027 | 100% | 57 units booked out of total 69 units |
About this project
Laxmi Narayan Mansion by Atharva Developers is a 48-unit project in Borivali West, Mumbai 400092, launched in July 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 74% complete.
Read full summary
Laxmi Narayan Mansion is a project by Atharva Developers in Borivali West, Mumbai 400092, registered with MahaRERA as P51800002218. It was launched in July 2017. It has 48 units in 1 building: 45 homes (2, 3 and 4 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in January 2022. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 74% complete, final finishes 5% complete.