Bhalla CHSL Jupiter - Venus, Mulund West
by Chetna Global · Mulund West, Mumbai 400080 · Map
- Launched
- Jul 20172 yrs 5 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 7 yrs 4 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 24 of 2596% · 29 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale24 booked out of 25 units
Rehab29 units for existing members
Total 54 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 25
- 3 BHK
- 15
- 4 BHK
- 12
- Other units
- 2
- Total units
- 54
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 25
- Rehab units
- 29
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 24 | |
| 100% | 100% | 10% | 24 | |
| 100% | 100% | 5% | – | |
| 100% | 100% | 5% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400080
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 4 yrs 8 mths |
| Possession date extended | By 7 yrs 4 mths | 2 of 3 |
| Possession date (MahaRERA) | Apr 2027 | May 2023 |
| Concrete structure (RCC) | 100% | 100% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 3 projects
- Vivanta, Mulund West
- Ishaan Enclave, Mulund West
- Kailash Residency, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vivanta | July 2017 | July 2022 | 100% | – |
| Ishaan Enclave | September 2017 | May 2023 | 53% | 11 units booked out of 29 units for sale |
| Kailash Residency | December 2017 | December 2026 | 100% | 20 units booked out of 20 units for sale |
About this project
Bhalla CHSL Jupiter - Venus by Chetna Global is a 54-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in July 2017 with possession due in April 2027. 24 units booked out of 25 units for sale. The concrete structure (RCC) is complete.
Read full summary
Bhalla CHSL Jupiter - Venus is a BMC-sanctioned project by Chetna Global in Mulund West, Mumbai 400080, registered with MahaRERA as P51800000906. It was launched in July 2017. It has 54 units in 2 buildings: 52 homes (2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 54 units, 25 are for sale and 29 are rehab units for existing members.
Its registered possession date is April 2027, extended by 7 years 4 months from the original December 2019. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.
24 units booked out of 25 units for sale (96%).