Skip to main content

Bhalla CHSL Jupiter - Venus, Mulund West

by Chetna Global · Mulund West, Mumbai 400080 · Map

Launched
Jul 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 7 yrs 4 mths
Concrete structure
100%Nearing possession
Booked (free sale)
24 of 2596% · 29 rehab units
Buildings
20.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale24 booked out of 25 units

Rehab29 units for existing members

Total 54 units. Rehab units are not for sale.

Project facts

2 BHK
25
3 BHK
15
4 BHK
12
Other units
2
Total units
54
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Free-sale units
25
Rehab units
29

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 5%Dec 2025: Final finishes 5%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%24
100%100%10%24
100%100%5%–
100%100%5%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400080

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths4 yrs 8 mths
Possession date extendedBy 7 yrs 4 mths2 of 3
Possession date (MahaRERA)Apr 2027May 2023
Concrete structure (RCC)100%100%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Bhalla CHSL Jupiter - Venus by Chetna Global is a 54-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in July 2017 with possession due in April 2027. 24 units booked out of 25 units for sale. The concrete structure (RCC) is complete.

Read full summary

Bhalla CHSL Jupiter - Venus is a BMC-sanctioned project by Chetna Global in Mulund West, Mumbai 400080, registered with MahaRERA as P51800000906. It was launched in July 2017. It has 54 units in 2 buildings: 52 homes (2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 54 units, 25 are for sale and 29 are rehab units for existing members.

Its registered possession date is April 2027, extended by 7 years 4 months from the original December 2019. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.

24 units booked out of 25 units for sale (96%).