Ishaan Enclave, Mulund West
by Ishaan Developers · Mulund West, Mumbai 400080 · Map
- Launched
- Sep 20174 yrs 8 mths originally promised
- Possession (MahaRERA)
- May 2023Extended by 1 yr
- Concrete structure
- 53%Mid-construction
- Booked (free sale)
- 11 of 2938% · 20 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale11 booked out of 29 units
Rehab20 units for existing members
Total 49 units. Rehab units are not for sale.
Project facts
- 1 RK
- 4
- 1 BHK
- 32
- 2 BHK
- 7
- 3 BHK
- 2
- 4 BHK
- 3
- Other units
- 1
- Total units
- 49
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 29
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 53% | 0% | 11 | |
| 100% | 53% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400080
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 8 mths | 3 yrs 6 mths |
| Possession date extended | By 1 yr | 3 of 4 |
| Possession date (MahaRERA) | May 2023 | Oct 2025 |
| Concrete structure (RCC) | 53% | 100% |
| Units booked (free sale) | 38% | 96% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 4 projects
- Mulund Narayan Pushp Chs Ltd, Mulund West
- Bhalla CHSL Jupiter - Venus, Mulund West
- Vivanta, Mulund West
- Kailash Residency, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mulund Narayan Pushp Chs Ltd | August 2017 | August 2024 | 100% | 20 units booked out of total 21 units |
| Bhalla CHSL Jupiter - Venus | July 2017 | April 2027 | 100% | 24 units booked out of 25 units for sale |
| Vivanta | July 2017 | July 2022 | 100% | – |
| Kailash Residency | December 2017 | December 2026 | 100% | 20 units booked out of 20 units for sale |
About this project
Ishaan Enclave by Ishaan Developers is a 49-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in September 2017 with possession due in May 2023. 11 units booked out of 29 units for sale. The concrete structure (RCC) is 53% complete.
Read full summary
Ishaan Enclave is a BMC-sanctioned project by Ishaan Developers in Mulund West, Mumbai 400080, registered with MahaRERA as P51800012610. It was launched in September 2017. It has 49 units in 1 building: 48 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 49 units, 29 are for sale and 20 are rehab units for existing members.
Possession was due in May 2023, after an extension of 1 year from the original May 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 53% complete, final finishes not started.
11 units booked out of 29 units for sale (38%).