Kailash Residency, Mulund West

by Tridev Shreeji Associates · Mulund West, Mumbai 400080 · Map

Launched
Dec 20174 yrs 8 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 4 yrs 4 mths
Concrete structure
100%Nearing possession
Booked (free sale)
20 of 20100% · 34 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 20 units

Rehab34 units for existing members

Land-owner share10 units, not for sale

Total 64 units. Rehab and land-owner units are not for sale.

Project facts

1 RK
8
1 BHK
16
2 BHK
26
3 BHK
5
4 BHK
1
Other units
8
Total units
64
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
20
Rehab units
34
Land-owner share (not for sale)
10
Reserved units
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services56%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 78%Dec 2025: Final finishes 78%Jul 2026: Final finishes 53%Oct 2026: Final finishes 56%Excavation 100%Concrete structure (RCC) 100%Final finishes 56%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%56%20
100%100%53%20
100%100%78%20
100%100%78%20

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400080

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 8 mths4 yrs 8 mths
Possession date extendedBy 4 yrs 4 mths2 of 3
Possession date (MahaRERA)Dec 2026May 2023
Concrete structure (RCC)100%100%
MahaRERA complaints (filed by or against the builder)01

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Kailash Residency by Tridev Shreeji Associates is a 64-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in December 2017 with possession due in December 2026. 20 units booked out of 20 units for sale. The concrete structure (RCC) is complete.

Read full summary

Kailash Residency is a BMC-sanctioned project by Tridev Shreeji Associates in Mulund West, Mumbai 400080, registered with MahaRERA as P51800014738. It was launched in December 2017. It has 64 units in 1 building: 56 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 64 units, 20 are for sale, 34 are rehab units for existing members and 10 are the land-owner's share, not for sale.

Its registered possession date is December 2026, extended by 4 years 4 months from the original August 2022. Construction: excavation complete, structure (RCC) complete, final finishes 56% complete.

20 units booked out of 20 units for sale (100%).