- Launched
- Jul 20175 yrs 5 mths originally promised
- Possession (MahaRERA)
- Apr 2028Extended by 5 yrs 4 mths
- Concrete structure
- 100%Ready to move
- Booked
- 378 of 38399%
- Buildings
- 31.8 acres
- MahaRERA complaints
- 58Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 1
- 1 BHK
- 143
- 2 BHK
- 191
- 3 BHK
- 41
- 4 BHK
- 3
- 5+ BHK
- 1
- Other units
- 3
- Total units
- 383
- Buildings
- 3
- Land
- 1.8 acres
- Phases
- 1
- MahaRERA complaints
- 58
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 378 | |
| 100% | 100% | 95% | 378 | |
| 100% | 100% | 73% | 378 | |
| 100% | 68% | 0% | 378 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400078
Projects with 150–800 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 5 mths | 5 yrs 10 mths |
| Possession date extended | By 5 yrs 4 mths | 3 of 4 |
| Possession date (MahaRERA) | Apr 2028 | Jan 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 99% | 85% |
| MahaRERA complaints (filed by or against the builder) | 58 | 0 |
The 4 projects
- Vaikunth Dham CHS Ltd, Bhandup West
- Platinum Heights, Bhandup West
- Shraddha Evoque, Bhandup West
- Daffodil Heights, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vaikunth Dham CHS Ltd | August 2017 | December 2022 | 100% | – |
| Platinum Heights | August 2017 | June 2027 | 100% | 224 units booked out of 263 units for sale |
| Shraddha Evoque | August 2017 | August 2026 | 100% | 569 units booked out of 612 units for sale |
| Daffodil Heights | September 2017 | April 2030 | 83% | 137 units booked out of 186 units for sale |
About this project
Avante by Sanjeevani Vyapaar LLP is a 383-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in July 2017 with possession due in April 2028. 378 units booked out of total 383 units. The concrete structure (RCC) is complete.
Read full summary
Avante is a BMC-sanctioned project by Sanjeevani Vyapaar LLP in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800001140. It was launched in July 2017. It has 383 units in 3 buildings: 380 homes (1 RK, 1 BHK, 2 BHK, 3 BHK, 4 BHK and 5+ BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2028, extended by 5 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
378 units booked out of total 383 units (99%).