Shraddha Evoque, Bhandup West

Ready to moveLapsed

by Shraddha Landmark Private Limited · Bhandup West, Mumbai 400078 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Aug 2026Extended by 2 yrs 8 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
569 of 61293% · 62 rehab units
Buildings
82.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale569 booked out of 612 units

Rehab62 units for existing members

Total 674 units. Rehab units are not for sale.

Project facts

1 BHK
444
2 BHK
195
Other units
35
Total units
674
Buildings
8
Land
2.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
612
Rehab units
62

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 98%Dec 2025: Concrete structure (RCC) 98%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%569
100%100%100%569
100%98%95%–
100%98%95%454

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400078

Projects with 300–1,300 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 4 mths5 yrs 4 mths
Possession date extendedBy 2 yrs 8 mths3 of 4
Possession date (MahaRERA)Aug 2026Nov 2027
Concrete structure (RCC)100%100%
Units booked (free sale)93%85%
MahaRERA complaints (filed by or against the builder)02

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Shraddha Evoque by Shraddha Landmark Private Limited is a 674-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in August 2017; its MahaRERA registration has lapsed. 569 units booked out of 612 units for sale. The concrete structure (RCC) is complete.

Read full summary

Shraddha Evoque is an SRA-sanctioned project by Shraddha Landmark Private Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800008864. It was launched in August 2017. It has 674 units in 8 buildings: 639 homes (1 and 2 BHK) and 35 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 674 units, 612 are for sale and 62 are rehab units for existing members.

Possession was due in August 2026, after an extension of 2 years 8 months from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

569 units booked out of 612 units for sale (93%).

Shraddha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA53
Total units across these projects9,707
Completed without extending the possession date16
Completed after an extension4
Lapsed5
Under construction28
Possession date extended on the builder's application18
Typical time from launch to 100% structure4 years
MahaRERA complaints (filed by or against the builder), all Shraddha projects14 (11 of 53 projects)

See all Shraddha projects →