Marathon Monte Carlo, Mulund West
Ready to move
by Marathon Realty Pvt Ltd · Mulund West, Mumbai 400080 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2023 – Dec 2026Extended in 1 of 2 phases
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 20.1 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 22
- 5+ BHK
- 25
- Total units
- 47
- Buildings
- 2
- Land
- 0.1 acres
- Phases
- 2
- MahaRERA complaints
- 2
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Marathon Monte Carlo-2 Ready to move Lapsed | P51800002662 | 19 | 100% | – | |
| Marathon Monte Carlo 3 Ready to move | P51800029900 | 28 | 100% | – |
Show updates by phase
Marathon Monte Carlo-2 (P51800002662)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 19 |
"–" means MahaRERA shows no figure for that update.
Marathon Monte Carlo 3 (P51800029900)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 100% | 100% | – | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | 15 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400080
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 2 mths | 4 yrs 4 mths |
| Possession date extended | Yes | 6 of 6 |
| Possession date (MahaRERA) | Dec 2023 – Dec 2026 | Jan 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | – | 96% |
| MahaRERA complaints (filed by or against the builder) | 2 | 0 |
The 6 projects
- Alag Marina, Mulund West
- Maverick Mooldeep, Mulund West
- Neptunes Lotus, Mulund West
- Mulund Mahavirdham Co. Op. Housing Soc. Ltd, Mulund West
- N And G Co Op Housing Soc Ltd, Mulund West
- Aakruti Aashvi Apartment, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Alag Marina | August 2017 | December 2026 | 95% | 24 units booked out of 24 units for sale |
| Maverick Mooldeep | August 2017 | October 2026 | 100% | 26 units booked out of 27 units for sale |
| Neptunes Lotus | August 2017 | April 2028 | 100% | 49 units booked out of total 61 units |
| Mulund Mahavirdham Co. Op. Housing Soc. Ltd | August 2017 | March 2027 | 100% | 38 units booked out of 38 units for sale |
| N And G Co Op Housing Soc Ltd | August 2017 | March 2027 | 100% | 20 units booked out of 21 units for sale |
| Aakruti Aashvi Apartment | August 2017 | June 2026 | 100% | 28 units booked out of total 36 units |
About this project
Marathon Monte Carlo by Marathon Realty Pvt Ltd is a 47-unit BMC-sanctioned project in Mulund West, Mumbai 400080, registered with MahaRERA in 2 phases, with possession dates from December 2023 to December 2026. The concrete structure (RCC) is complete.
Read full summary
Marathon Monte Carlo is a BMC-sanctioned project by Marathon Realty Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as 2 phases (P51800002662, P51800029900). The first phase was launched in August 2017. Together the phases have 47 units in 2 buildings, with 4 and 5+ BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.
The phases' registered possession dates run from December 2023 to December 2026; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 100% complete. Both phases have their structure complete.
Marathon's track record in Mumbai
MahaRERA projects registered 2017–2024 in Mumbai
| Projects registered with MahaRERA | 11 |
|---|---|
| Total units across these projects | 818 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 2 |
| Lapsed | 6 |
| Under construction | 3 |
| Possession date extended on the builder's application | 5 |
| Typical time from launch to 100% structure | 4 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Marathon projects | 11 (5 of 11 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.