Marathon Monte Carlo, Mulund West

Ready to move

by Marathon Realty Pvt Ltd · Mulund West, Mumbai 400080 · Map

Launched
Aug 2017First of 2 phases
Possession (MahaRERA)
Dec 2023 – Dec 2026Extended in 1 of 2 phases
Concrete structure
100%Weighted across 2 phases
Booked
–
Buildings
20.1 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
22
5+ BHK
25
Total units
47
Buildings
2
Land
0.1 acres
Phases
2
MahaRERA complaints
2

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Marathon Monte Carlo-2
Ready to move Lapsed
P5180000266219100%–
Marathon Monte Carlo 3
Ready to move
P5180002990028100%–
Show updates by phase

Marathon Monte Carlo-2 (P51800002662)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%19

"–" means MahaRERA shows no figure for that update.

Marathon Monte Carlo 3 (P51800029900)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%100%100%–
100%100%95%–
100%100%95%15

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation40%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 40%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 97%Dec 2025: Final finishes 97%Jul 2026: Final finishes 100%Concrete structure (RCC) 100%Final finishes 100%Excavation 40%

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 2 mths4 yrs 4 mths
Possession date extendedYes6 of 6
Possession date (MahaRERA)Dec 2023 – Dec 2026Jan 2027
Concrete structure (RCC)100%100%
Units booked–96%
MahaRERA complaints (filed by or against the builder)20

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Marathon Monte Carlo by Marathon Realty Pvt Ltd is a 47-unit BMC-sanctioned project in Mulund West, Mumbai 400080, registered with MahaRERA in 2 phases, with possession dates from December 2023 to December 2026. The concrete structure (RCC) is complete.

Read full summary

Marathon Monte Carlo is a BMC-sanctioned project by Marathon Realty Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as 2 phases (P51800002662, P51800029900). The first phase was launched in August 2017. Together the phases have 47 units in 2 buildings, with 4 and 5+ BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.

The phases' registered possession dates run from December 2023 to December 2026; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 100% complete. Both phases have their structure complete.

Marathon's track record in Mumbai

MahaRERA projects registered 2017–2024 in Mumbai

Projects registered with MahaRERA11
Total units across these projects818
Completed without extending the possession date0
Completed after an extension2
Lapsed6
Under construction3
Possession date extended on the builder's application5
Typical time from launch to 100% structure4 years 6 months
MahaRERA complaints (filed by or against the builder), all Marathon projects11 (5 of 11 projects)