- Launched
- Aug 20174 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2022Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 95%Mid-construction
- Booked
- –
- Buildings
- 10.8 acres
- MahaRERA complaints
- 8Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 34
- 3 BHK
- 18
- Total units
- 53
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 95% | – | |
| 100% | 95% | 95% | – | |
| 100% | 95% | 95% | 49 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 4 mths | 1 yr 10 mths |
| Possession date extended | By 1 yr | 5 of 6 |
| Possession date (MahaRERA) | Dec 2022 | May 2026 |
| Concrete structure (RCC) | 95% | 81% |
| Units booked | – | 77% |
| MahaRERA complaints (filed by or against the builder) | 8 | 2 |
The 6 projects
- Victory Platinum, Kandivali West
- Kandivali Geeta Sadan Chs Ltd, Kandivali West
- Kavya Kcd Prestine, Kandivali West
- Krishna, Kandivali West
- Buildings on portion of Sub plot A CTS no 671A 662A 610A etc of Kandivali, Kandivali West
- Building on Sub Plot F of CTS No 283 A and 238 B of Kandivali West, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Victory Platinum | August 2017 | December 2019 | 100% | 57 units booked out of total 95 units |
| Kandivali Geeta Sadan Chs Ltd | August 2017 | April 2025 | 95% | 22 units booked out of 23 units for sale |
| Kavya Kcd Prestine | August 2017 | September 2028 | 64% | 3 units booked out of 18 units for sale |
| Krishna | August 2017 | December 2028 | 67% | 37 units booked out of total 121 units |
| Buildings on portion of Sub plot A CTS no 671A 662A 610A etc of Kandivali | August 2017 | October 2020 | 100% | 81 units booked out of total 85 units |
| Building on Sub Plot F of CTS No 283 A and 238 B of Kandivali West | August 2017 | July 2027 | 43% | 84 units booked out of total 89 units |
About this project
Tanna Heights by Tanna Housing is a 53-unit project in Kandivali West, Mumbai 400067, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 95% complete.
Read full summary
Tanna Heights is a project by Tanna Housing in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800002925. It was launched in August 2017. It has 53 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2022, after an extension of 1 year from the original December 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes 95% complete.