Al Marjaan, Jogeshwari West

Ready to move

by Town Developers · Jogeshwari West, Mumbai 400102 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Dec 2019Extended by 1 yr
Concrete structure
100%Ready to move
Booked
–
Buildings
11.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
46
3 BHK
1
Total units
47
Buildings
1
Land
1.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%–
100%100%90%–
100%100%90%46

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400102

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 4 mths4 yrs 4 mths
Possession date extendedBy 1 yr4 of 5
Possession date (MahaRERA)Dec 2019Dec 2025
Concrete structure (RCC)100%50%
Units booked–43%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Al Marjaan by Town Developers is a 47-unit project in Jogeshwari West, Mumbai 400102, launched in August 2017 with possession due in December 2019. The concrete structure (RCC) is complete.

Read full summary

Al Marjaan is a project by Town Developers in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800003556. It was launched in August 2017. It has 47 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2019, after an extension of 1 year from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.