Elite Avenue, Jogeshwari West

Ready to moveLapsed

by Abdul Sattar Suleman & Others · Jogeshwari West, Mumbai 400102 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
41 of 7853%
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
73
Other units
5
Total units
78
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 16%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 65%Dec 2025: Final finishes 90%Jul 2026: Final finishes 98%Oct 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%41
100%100%98%41
100%100%90%41
100%16%65%41

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400102

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 4 mths3 yrs 10 mths
Possession date extendedBy 2 yrs5 of 6
Possession date (MahaRERA)Dec 2025Dec 2023
Concrete structure (RCC)100%50%
Units booked53%62%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Elite Avenue by Abdul Sattar Suleman & Others is a 78-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in August 2017; its MahaRERA registration has lapsed. 41 units booked out of total 78 units. The concrete structure (RCC) is complete.

Read full summary

Elite Avenue is a BMC-sanctioned project by Abdul Sattar Suleman & Others in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800004191. It was launched in August 2017. It has 78 units in 1 building: 73 homes (2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 2 years from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

41 units booked out of total 78 units (53%).