Proposed Redevelopment Of Cts No 52, Shagufa Municipal Employees Chs Ltd, Jogeshwari West, Jogeshwari West

Lapsed

by Aftab Constructions · Jogeshwari West, Mumbai 400102 · Map

Launched
Sep 20172 yrs 3 mths originally promised
Possession (MahaRERA)
Jun 2024Extended by 4 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked (free sale)
7 of 3918% · 51 rehab units
Buildings
20.7 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 39 units

Rehab51 units for existing members

Total 90 units. Rehab units are not for sale.

Project facts

1 BHK
21
2 BHK
48
3 BHK
13
Other units
8
Total units
90
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
2
Free-sale units
39
Rehab units
51

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Oct 2026: Excavation 50%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%7
50%0%0%7
50%0%0%7
50%0%0%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400102

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400102
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths4 yrs 1 mth
Possession date extendedBy 4 yrs 6 mths3 of 4
Possession date (MahaRERA)Jun 2024Dec 2023
Concrete structure (RCC)0%75%
MahaRERA complaints (filed by or against the builder)20

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Proposed Redevelopment Of Cts No 52, Shagufa Municipal Employees Chs Ltd, Jogeshwari West by Aftab Constructions is a 90-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in September 2017; its MahaRERA registration has lapsed. 7 units booked out of 39 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Proposed Redevelopment Of Cts No 52, Shagufa Municipal Employees Chs Ltd, Jogeshwari West is a BMC-sanctioned project by Aftab Constructions in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800012475. It was launched in September 2017. It has 90 units in 2 buildings: 82 homes (1, 2 and 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 90 units, 39 are for sale and 51 are rehab units for existing members.

Possession was due in June 2024, after an extension of 4 years 6 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started.

7 units booked out of 39 units for sale (18%).