Premsagar, Santacruz West

Ready to moveLapsed

by Ankur Premises Developers LLP · Santacruz West, Mumbai 400054 · Map

Launched
Aug 20173 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 4 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
11 of 1669% · 9 in Jul 2026
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
13
2 BHK
3
Total units
16
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 80%Dec 2025: Excavation 80%Jul 2026: Excavation 80%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%11
80%0%0%9
80%0%0%9
80%0%0%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400054

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths2 yrs 4 mths
Possession date extendedBy 4 yrs 6 mths4 of 5
Possession date (MahaRERA)Dec 2025Dec 2023
Concrete structure (RCC)100%97%
Units booked69%55%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Premsagar by Ankur Premises Developers LLP is a 16-unit project in Santacruz West, Mumbai 400054, launched in August 2017; its MahaRERA registration has lapsed. 11 units booked out of total 16 units. The concrete structure (RCC) is complete.

Read full summary

Premsagar is a project by Ankur Premises Developers LLP in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800004056. It was launched in August 2017. It has 16 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 4 years 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

11 units booked out of total 16 units (69%). Since the July 2026 update, 2 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from July 2025 to December 2025.