Radius Residency and Anand Bhuvan, Santacruz West
Lapsed
by Radius Project Developers LLP · Santacruz West, Mumbai 400054 · Map
- Launched
- Aug 20176 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2023Not extendedWhat does Lapsed mean?
- Concrete structure
- 97%Mid-construction
- Booked
- 4 of 2516%
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 1
- 3 BHK
- 5
- 4 BHK
- 18
- Other units
- 1
- Total units
- 25
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 0% | 4 | |
| 100% | 97% | 0% | – | |
| 100% | 97% | 0% | – | |
| 100% | 97% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400054
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 3 yrs 10 mths |
| Possession date extended | No | 3 of 3 |
| Possession date (MahaRERA) | Dec 2023 | Mar 2027 |
| Concrete structure (RCC) | 97% | 100% |
| Units booked | 16% | 69% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Premsagar, Santacruz West
- Pearl 2, Santacruz West
- M.K Heritage, Santacruz West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Premsagar | August 2017 | December 2025 | 100% | 11 units booked out of total 16 units |
| Pearl 2 | August 2017 | March 2027 | 100% | 14 units booked out of total 15 units |
| M.K Heritage | January 2018 | December 2030 | 45% | 0 units booked out of total 15 units |
About this project
Radius Residency and Anand Bhuvan by Radius Project Developers LLP is a 25-unit SRA-sanctioned project in Santacruz West, Mumbai 400054, launched in August 2017; its MahaRERA registration has lapsed. 4 units booked out of total 25 units. The concrete structure (RCC) is 97% complete.
Read full summary
Radius Residency and Anand Bhuvan is an SRA-sanctioned project by Radius Project Developers LLP in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800011593. It was launched in August 2017. It has 25 units in 2 buildings: 24 homes (2, 3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 97% complete, final finishes not started.
4 units booked out of total 25 units (16%).