Orchid Metropolis, Kurla East
Ready to moveLapsed
by Bharat Mahan Developers & Builders · Kurla East, Mumbai 400024 · Map
- Launched
- Aug 201711 mths originally promised
- Possession (MahaRERA)
- Jul 2024Extended by 6 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 123 of 13095%
- Buildings
- 11 acre
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 12
- 1 BHK
- 35
- 2 BHK
- 46
- Other units
- 37
- Total units
- 130
- Buildings
- 1
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 123 | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 123 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400024
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 11 mths | 4 yrs 2 mths |
| Possession date extended | By 6 yrs | 5 of 6 |
| Possession date (MahaRERA) | Jul 2024 | Dec 2024 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 95% | 98% |
| MahaRERA complaints (filed by or against the builder) | 6 | 2 |
The 6 projects
- Nehru Nagar Mangal Prabhat Chs Ltd Building No-9, Kurla East
- Ekta Co-Op Hsg Society, Kurla East
- Serene Shelter, Kurla East
- Sonal Heights, Kurla East
- Nehru Nagar Panchratna Chs Ltd, Bldg. No.5, Kurla East
- Nehru Nagar Sharada Chs Ltd Bldg No. 62, Kurla East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nehru Nagar Mangal Prabhat Chs Ltd Building No-9 | August 2017 | July 2022 | 50% | – |
| Ekta Co-Op Hsg Society | August 2017 | December 2024 | 100% | 119 units booked out of total 141 units |
| Serene Shelter | August 2017 | December 2024 | 44% | 120 units booked out of total 120 units |
| Sonal Heights | August 2017 | October 2021 | 100% | 36 units booked out of 60 units for sale |
| Nehru Nagar Panchratna Chs Ltd, Bldg. No.5 | January 2018 | December 2025 | 100% | 82 units booked out of total 84 units |
| Nehru Nagar Sharada Chs Ltd Bldg No. 62 | January 2018 | December 2025 | 100% | 56 units booked out of total 56 units |
About this project
Orchid Metropolis by Bharat Mahan Developers & Builders is a 130-unit SRA-sanctioned project in Kurla East, Mumbai 400024, launched in August 2017; its MahaRERA registration has lapsed. 123 units booked out of total 130 units. The concrete structure (RCC) is complete.
Read full summary
Orchid Metropolis is an SRA-sanctioned project by Bharat Mahan Developers & Builders in Kurla East, Mumbai 400024, registered with MahaRERA as P51800005064. It was launched in August 2017. It has 130 units in 1 building: 93 homes (1 RK, 1 BHK and 2 BHK) and 37 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in July 2024, after an extension of 6 years from the original July 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
123 units booked out of total 130 units (95%).