Orchid Metropolis, Kurla East

Ready to moveLapsed

by Bharat Mahan Developers & Builders · Kurla East, Mumbai 400024 · Map

Launched
Aug 201711 mths originally promised
Possession (MahaRERA)
Jul 2024Extended by 6 yrsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
123 of 13095%
Buildings
11 acre
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
12
1 BHK
35
2 BHK
46
Other units
37
Total units
130
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%123
100%100%90%–
100%100%90%–
100%100%90%123

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400024

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400024
MeasureThis projectSimilar projects
Launch to possession (as first promised)11 mths4 yrs 2 mths
Possession date extendedBy 6 yrs5 of 6
Possession date (MahaRERA)Jul 2024Dec 2024
Concrete structure (RCC)100%100%
Units booked95%98%
MahaRERA complaints (filed by or against the builder)62

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Orchid Metropolis by Bharat Mahan Developers & Builders is a 130-unit SRA-sanctioned project in Kurla East, Mumbai 400024, launched in August 2017; its MahaRERA registration has lapsed. 123 units booked out of total 130 units. The concrete structure (RCC) is complete.

Read full summary

Orchid Metropolis is an SRA-sanctioned project by Bharat Mahan Developers & Builders in Kurla East, Mumbai 400024, registered with MahaRERA as P51800005064. It was launched in August 2017. It has 130 units in 1 building: 93 homes (1 RK, 1 BHK and 2 BHK) and 37 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in July 2024, after an extension of 6 years from the original July 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

123 units booked out of total 130 units (95%).