Sonal Heights, Kurla East

Lapsed

by Sonal Dev-Con Pvt Ltd · Kurla East, Mumbai 400024 · Map

Launched
Aug 20173 yrs 2 mths originally promised
Possession (MahaRERA)
Oct 2021Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked (free sale)
36 of 6060% · 81 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale36 booked out of 60 units

Rehab81 units for existing members

Total 141 units. Rehab units are not for sale.

Project facts

1 BHK
107
2 BHK
15
Other units
19
Total units
141
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
60
Rehab units
81
Reserved units
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 75%Dec 2025: Final finishes 75%Jul 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%36
100%100%75%36
100%100%75%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400024

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400024
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 2 mths3 yrs 5 mths
Possession date extendedBy 1 yr4 of 5
Possession date (MahaRERA)Oct 2021Dec 2024
Concrete structure (RCC)100%100%
Units booked (free sale)60%96%
MahaRERA complaints (filed by or against the builder)05

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Sonal Heights by Sonal Dev-Con Pvt Ltd is a 141-unit SRA-sanctioned project in Kurla East, Mumbai 400024, launched in August 2017; its MahaRERA registration has lapsed. 36 units booked out of 60 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sonal Heights is an SRA-sanctioned project by Sonal Dev-Con Pvt Ltd in Kurla East, Mumbai 400024, registered with MahaRERA as P51800008992. It was launched in August 2017. It has 141 units in 1 building: 122 homes (1 and 2 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 141 units, 60 are for sale and 81 are rehab units for existing members.

Possession was due in October 2021, after an extension of 1 year from the original October 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

36 units booked out of 60 units for sale (60%).