- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2025Extended in both phasesWhat does Lapsed mean?
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- 84 of 8599%
- Buildings
- 20.2 acres
- MahaRERA complaints
- 12Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 85
- Total units
- 85
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 2
- MahaRERA complaints
- 12
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Swiz Heights Ready to move Lapsed | P51800005779 | 60 | 100% | 98% | |
| Swiz Heights Phase 2 Nearing possession Lapsed | P51800033525 | 25 | 100% | 100% |
Show updates by phase
Swiz Heights (P51800005779)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 59 | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | 59 |
"–" means MahaRERA shows no figure for that update.
Swiz Heights Phase 2 (P51800033525)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 25 | |
| 100% | 100% | 20% | – | |
| 100% | 100% | 20% | – | |
| 100% | 100% | 20% | 25 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400053
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 7 mths | 6 yrs 2 mths |
| Possession date extended | Yes | 4 of 6 |
| Possession date (MahaRERA) | Dec 2025 | Jul 2026 |
| Concrete structure (RCC) | 100% | 98% |
| Units booked | 99% | 87% |
| MahaRERA complaints (filed by or against the builder) | 12 | 4 |
The 6 projects
- Eleganzia Royale, Andheri West
- Hubtown Premiere Residences - Malibu, Andheri West
- Hubtown Premiere Residences - Bel Air, Andheri West
- Royale, Andheri West
- Gaurav Legend, Andheri West
- Vengurlekars Chaitra, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Eleganzia Royale | August 2017 | March 2024 | 100% | 77 units booked out of total 88 units |
| Hubtown Premiere Residences - Malibu | August 2017 | July 2029 | 100% | 81 units booked out of total 81 units |
| Hubtown Premiere Residences - Bel Air | August 2017 | July 2026 | 95% | 69 units booked out of total 81 units |
| Royale | August 2017 | September 2026 | 100% | 34 units booked out of 39 units for sale |
| Gaurav Legend | August 2017 | June 2026 | 51% | 64 units booked out of total 65 units |
| Vengurlekars Chaitra | August 2017 | December 2021 | 0% | 33 units booked out of 46 units for sale |
About this project
Swiz Heights by Mohid Construction Co is an 85-unit SRA-sanctioned project in Andheri West, Mumbai 400053, registered with MahaRERA in 2 phases, with possession due in December 2025. 84 units booked out of total 85 units. The concrete structure (RCC) is complete.
Read full summary
Swiz Heights is an SRA-sanctioned project by Mohid Construction Co in Andheri West, Mumbai 400053, registered with MahaRERA as 2 phases (P51800005779, P51800033525). The first phase was launched in August 2017. Together the phases have 85 units in 2 buildings, with 1 BHK homes as registered with MahaRERA. Both phases are lapsed on MahaRERA.
The registered possession date is December 2025; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 73% complete. Both phases have their structure complete.
84 units booked out of total 85 units (99%).