- Launched
- Aug 20175 yrs 11 mths originally promised
- Possession (MahaRERA)
- Sep 2026Extended by 3 yrs 2 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 34 of 3987% · 31 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale34 booked out of 39 units
Rehab31 units for existing members
Total 70 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 69
- Other units
- 1
- Total units
- 70
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 3
- Free-sale units
- 39
- Rehab units
- 31
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 65% | 34 | |
| 100% | 100% | 65% | 34 | |
| 80% | 89% | 0% | 33 | |
| 100% | 67% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400053
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 11 mths | 5 yrs 1 mth |
| Possession date extended | By 3 yrs 2 mths | 4 of 6 |
| Possession date (MahaRERA) | Sep 2026 | Mar 2026 |
| Concrete structure (RCC) | 100% | 98% |
| Units booked (free sale) | 87% | 93% |
| MahaRERA complaints (filed by or against the builder) | 3 | 9 |
The 6 projects
- Gaurav Legend, Andheri West
- Vengurlekars Chaitra, Andheri West
- Hubtown Premiere Residences - Malibu, Andheri West
- Hubtown Premiere Residences - Bel Air, Andheri West
- Swiz Heights, Andheri West
- Eleganzia Royale, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Gaurav Legend | August 2017 | June 2026 | 51% | 64 units booked out of total 65 units |
| Vengurlekars Chaitra | August 2017 | December 2021 | 0% | 33 units booked out of 46 units for sale |
| Hubtown Premiere Residences - Malibu | August 2017 | July 2029 | 100% | 81 units booked out of total 81 units |
| Hubtown Premiere Residences - Bel Air | August 2017 | July 2026 | 95% | 69 units booked out of total 81 units |
| Swiz Heights | August 2017 | Dec 2025 | 100% | 84 units booked out of total 85 units |
| Eleganzia Royale | August 2017 | March 2024 | 100% | 77 units booked out of total 88 units |
About this project
Royale by Khoker Synergy Developers is a 70-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in August 2017; its MahaRERA registration has lapsed. 34 units booked out of 39 units for sale. The concrete structure (RCC) is complete.
Read full summary
Royale is a BMC-sanctioned project by Khoker Synergy Developers in Andheri West, Mumbai 400053, registered with MahaRERA as P51800006143. It was launched in August 2017. It has 70 units in 1 building: 69 homes (2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 70 units, 39 are for sale and 31 are rehab units for existing members.
Possession was due in September 2026, after an extension of 3 years 2 months from the original July 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 65% complete.
34 units booked out of 39 units for sale (87%).