Kakad Classic, Bandra West
Ready to moveLapsed
by Niraj Kakad Developers LLP · Bandra West, Mumbai 400050 · Map
- Launched
- Aug 20171 yr 11 mths originally promised
- Possession (MahaRERA)
- Jan 2021Extended by 1 yr 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 11 of 11100%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 3 BHK
- 9
- 5+ BHK
- 1
- Total units
- 11
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 93% | 11 | |
| 100% | 100% | 93% | – | |
| 100% | 100% | 93% | – | |
| 100% | 100% | 93% | 11 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400050
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 11 mths | 5 yrs 4 mths |
| Possession date extended | By 1 yr 6 mths | 4 of 6 |
| Possession date (MahaRERA) | Jan 2021 | Sep 2024 |
| Concrete structure (RCC) | 100% | 55% |
| Units booked | 100% | 44% |
| MahaRERA complaints (filed by or against the builder) | 2 | 0 |
The 6 projects
- Crown, Bandra West
- Westside, Bandra West
- Hiland Hub, Bandra West
- Epitome, Bandra West
- White House, Bandra West
- Pali Darshan Chs Ltd, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Crown | August 2017 | November 2025 | 20% | 4 units booked out of total 13 units |
| Westside | August 2017 | March 2028 | 100% | 18 units booked out of total 19 units |
| Hiland Hub | August 2017 | July 2023 | 40% | – |
| Epitome | August 2017 | December 2019 | 70% | – |
| White House | August 2017 | June 2027 | 30% | 0 units booked out of 16 units for sale |
| Pali Darshan Chs Ltd | July 2017 | June 2019 | 100% | 8 units booked out of total 14 units |
About this project
Kakad Classic by Niraj Kakad Developers LLP is an 11-unit project in Bandra West, Mumbai 400050, launched in August 2017; its MahaRERA registration has lapsed. 11 units booked out of total 11 units. The concrete structure (RCC) is complete.
Read full summary
Kakad Classic is a project by Niraj Kakad Developers LLP in Bandra West, Mumbai 400050, registered with MahaRERA as P51800005809. It was launched in August 2017. It has 11 units in 1 building, with 1, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in January 2021, after an extension of 1 year 6 months from the original July 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 93% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
11 units booked out of total 11 units (100%).