Skip to main content

White House, Bandra West

by Omega Enterprises · Bandra West, Mumbai 400050 · Map

Launched
Aug 20177 yrs 4 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 2 yrs 6 mths
Concrete structure
30%Mid-construction
Booked (free sale)
0 of 160% · 15 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 16 units

Rehab15 units for existing members

Total 31 units. Rehab units are not for sale.

Project facts

1 BHK
6
2 BHK
18
3 BHK
6
Other units
1
Total units
31
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
16
Rehab units
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)30%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 30%Oct 2026: Concrete structure (RCC) 30%Dec 2024: Final finishes 20%Dec 2025: Final finishes 20%Jul 2026: Final finishes 0%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 30%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%30%20%0
100%30%0%0
100%50%20%0
100%50%20%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400050

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 4 mths3 yrs 10 mths
Possession date extendedBy 2 yrs 6 mths4 of 6
Possession date (MahaRERA)Jun 2027Jun 2022
Concrete structure (RCC)30%53%
Units booked (free sale)0%100%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

White House by Omega Enterprises is a 31-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in August 2017 with possession due in June 2027. 0 units booked out of 16 units for sale. The concrete structure (RCC) is 30% complete.

Read full summary

White House is a BMC-sanctioned project by Omega Enterprises in Bandra West, Mumbai 400050, registered with MahaRERA as P51800003392. It was launched in August 2017. It has 31 units in 1 building: 30 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 16 are for sale and 15 are rehab units for existing members.

Its registered possession date is June 2027, extended by 2 years 6 months from the original December 2024. Construction: excavation complete, structure (RCC) 30% complete, final finishes 20% complete.

0 units booked out of 16 units for sale (0%).