Proposed Redevelopment of Sugam Apartment, Mulund East
Lapsed
by Jay Builders · Mulund East, Mumbai 400081 · Map
- Launched
- Aug 20171 yr 5 mths originally promised
- Possession (MahaRERA)
- Dec 2022Extended by 3 yrs 11 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 29 of 4959%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 16
- 2 BHK
- 32
- Other units
- 1
- Total units
- 49
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 76% | 29 | |
| 100% | 100% | 76% | – | |
| 100% | 100% | 76% | – | |
| 100% | 100% | 76% | 29 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400081
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 5 mths | 3 yrs 10 mths |
| Possession date extended | By 3 yrs 11 mths | 5 of 6 |
| Possession date (MahaRERA) | Dec 2022 | Jun 2024 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 59% | 51% |
| MahaRERA complaints (filed by or against the builder) | 0 | 2 |
The 6 projects
- Mulund Ravi Kailash, Mulund East
- Shiv Chandra Sra Chs, Mulund East
- Rbi Employees Shree Sahawas Co Op Hsg Soc Ltd, Mulund East
- Yashashree, Mulund East
- Awantika Chs Ltd, Mulund East
- Valeria, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mulund Ravi Kailash | August 2017 | October 2021 | 100% | – |
| Shiv Chandra Sra Chs | August 2017 | December 2023 | 100% | 29 units booked out of total 56 units |
| Rbi Employees Shree Sahawas Co Op Hsg Soc Ltd | August 2017 | April 2028 | 70% | 8 units booked out of 16 units for sale |
| Yashashree | August 2017 | April 2029 | 100% | 17 units booked out of 36 units for sale |
| Awantika Chs Ltd | August 2017 | December 2024 | 100% | 30 units booked out of total 31 units |
| Valeria | August 2017 | June 2021 | 80% | – |
About this project
Proposed Redevelopment of Sugam Apartment by Jay Builders is a 49-unit project in Mulund East, Mumbai 400081, launched in August 2017; its MahaRERA registration has lapsed. 29 units booked out of total 49 units. The concrete structure (RCC) is complete.
Read full summary
Proposed Redevelopment of Sugam Apartment is a project by Jay Builders in Mulund East, Mumbai 400081, registered with MahaRERA as P51800007379. It was launched in August 2017. It has 49 units in 1 building: 48 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2022, after an extension of 3 years 11 months from the original January 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 76% complete.
29 units booked out of total 49 units (59%).