Mulund Ravi Kailash, Mulund East

Lapsed

by M Patankar Build Cons Private Limited · Mulund East, Mumbai 400081 · Map

Launched
Aug 20172 yrs 2 mths originally promised
Possession (MahaRERA)
Oct 2021Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.2 acres
MahaRERA complaints
14Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
14
2 BHK
13
3 BHK
14
Other units
10
Total units
51
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 75%Dec 2025: Final finishes 75%Jul 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%–
100%100%75%–
100%100%75%43

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400081

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 2 mths3 yrs 10 mths
Possession date extendedBy 2 yrs5 of 6
Possession date (MahaRERA)Oct 2021Jun 2024
Concrete structure (RCC)100%100%
Units booked–52%
MahaRERA complaints (filed by or against the builder)141

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Mulund Ravi Kailash by M Patankar Build Cons Private Limited is a 51-unit project in Mulund East, Mumbai 400081, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Mulund Ravi Kailash is a project by M Patankar Build Cons Private Limited in Mulund East, Mumbai 400081, registered with MahaRERA as P51800009931. It was launched in August 2017. It has 51 units in 1 building: 41 homes (1, 2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in October 2021, after an extension of 2 years from the original October 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.