Skip to main content

Ace and Matchpoint, Mulund West

by Ricardo Constructions Private Limited · Mulund West, Mumbai 400080 · Map

Launched
Aug 20173 yrs 7 mths originally promised
Possession (MahaRERA)
Jun 2028Extended by 7 yrs 3 mths
Concrete structure
51%Mid-construction
Booked
341 of 39786% · 342 in Jul 2026
Buildings
10.3 acres
MahaRERA complaints
103Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
315
3 BHK
82
Total units
397
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
103

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)51%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 44%Dec 2025: Concrete structure (RCC) 44%Jul 2026: Concrete structure (RCC) 51%Oct 2026: Concrete structure (RCC) 51%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 51%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%51%0%341
100%51%0%342
100%44%0%–
100%44%0%322

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400080

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths5 yrs 4 mths
Possession date extendedBy 7 yrs 3 mths4 of 5
Possession date (MahaRERA)Jun 2028Dec 2024
Concrete structure (RCC)51%80%
Units booked86%75%
MahaRERA complaints (filed by or against the builder)10334

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Ace and Matchpoint by Ricardo Constructions Private Limited is a 397-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in August 2017 with possession due in June 2028. 341 units booked out of total 397 units. The concrete structure (RCC) is 51% complete.

Read full summary

Ace and Matchpoint is a BMC-sanctioned project by Ricardo Constructions Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800007641. It was launched in August 2017. It has 397 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2028, extended by 7 years 3 months from the original March 2021. Construction: excavation complete, structure (RCC) 51% complete, final finishes not started.

341 units booked out of total 397 units (86%). Since the July 2026 update, the possession date has moved from March 2026 to June 2028.

Ricardo's track record in Mumbai

MahaRERA projects registered 2017–2017 in Mumbai

Projects registered with MahaRERA3
Total units across these projects912
Completed without extending the possession date0
Completed after an extension0
Lapsed0
Under construction3
Possession date extended on the builder's application3
MahaRERA complaints (filed by or against the builder), all Ricardo projects170 (3 of 3 projects)

See all Ricardo projects →