A And O Excellente, Mulund West

Lapsed

by Riddhi Siddhi Corporation · Mulund West, Mumbai 400080 · Map

Launched
Aug 20173 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2022Extended by 1 yr 6 mthsWhat does Lapsed mean?
Concrete structure
80%Mid-construction
Booked
471 of 54487%
Buildings
11 acre
MahaRERA complaints
34Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
534
3 BHK
10
Total units
544
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
34

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 80%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%80%471
100%80%80%–
100%80%80%–
100%80%80%471

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400080

Projects with 250–1,100 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 10 mths6 yrs 3 mths
Possession date extendedBy 1 yr 6 mths4 of 5
Possession date (MahaRERA)Dec 2022Dec 2026
Concrete structure (RCC)80%51%
Units booked87%58%
MahaRERA complaints (filed by or against the builder)3448

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

A And O Excellente by Riddhi Siddhi Corporation is a 544-unit project in Mulund West, Mumbai 400080, launched in August 2017; its MahaRERA registration has lapsed. 471 units booked out of total 544 units. The concrete structure (RCC) is 80% complete.

Read full summary

A And O Excellente is a project by Riddhi Siddhi Corporation in Mulund West, Mumbai 400080, registered with MahaRERA as P51800008399. It was launched in August 2017. It has 544 units in 1 building, with 1 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2022, after an extension of 1 year 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes 80% complete.

471 units booked out of total 544 units (87%).