Nirmal Lifestyle-Blu Diamond-One Edition, Mulund West

Lapsed

by Nirmal Lifestyle Ltd · Mulund West, Mumbai 400080 · Map

Launched
Aug 20172 yrs originally promised
Possession (MahaRERA)
Dec 2024Extended by 5 yrs 4 mthsWhat does Lapsed mean?
Concrete structure
67%Mid-construction
Booked
250 of 38565% · 237 in Dec 2024
Buildings
10.3 acres
MahaRERA complaints
48Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
54
2 BHK
331
Total units
385
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
48

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)67%
Finishes, lifts and services8%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Oct 2026Dec 2024: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 67%Oct 2026: Concrete structure (RCC) 67%Dec 2024: Final finishes 8%Oct 2026: Final finishes 8%Excavation 100%Concrete structure (RCC) 67%Final finishes 8%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%67%8%250
100%67%8%237

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs5 yrs 10 mths
Possession date extendedBy 5 yrs 4 mths5 of 6
Possession date (MahaRERA)Dec 2024Jun 2026
Concrete structure (RCC)67%66%
Units booked65%86%
MahaRERA complaints (filed by or against the builder)4836

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Nirmal Lifestyle-Blu Diamond-One Edition by Nirmal Lifestyle Ltd is a 385-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in August 2017; its MahaRERA registration has lapsed. 250 units booked out of total 385 units. The concrete structure (RCC) is 67% complete.

Read full summary

Nirmal Lifestyle-Blu Diamond-One Edition is a BMC-sanctioned project by Nirmal Lifestyle Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800006693. It was launched in August 2017. It has 385 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 5 years 4 months from the original August 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 67% complete, final finishes 8% complete.

250 units booked out of total 385 units (65%). Since the December 2024 update, 13 more units have been booked and the possession date has moved from August 2019 to December 2024.