Raj Shivganga, Malad West

Lapsed

by Raj Arcades & Enclaves Private Limited · Malad West, Mumbai 400064 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Dec 2019Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
93 of 11581%
Buildings
10.5 acres
MahaRERA complaints
19Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
15
2 BHK
82
3 BHK
18
Total units
115
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services85%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 85%Dec 2025: Final finishes 85%Jul 2026: Final finishes 85%Oct 2026: Final finishes 85%Excavation 100%Concrete structure (RCC) 100%Final finishes 85%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%85%93
100%100%85%–
100%100%85%–
100%100%85%93

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 4 mths6 yrs 4 mths
Possession date extendedBy 1 yr4 of 6
Possession date (MahaRERA)Dec 2019Dec 2026
Concrete structure (RCC)100%61%
Units booked81%68%
MahaRERA complaints (filed by or against the builder)195

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Raj Shivganga by Raj Arcades & Enclaves Private Limited is a 115-unit project in Malad West, Mumbai 400064, launched in August 2017; its MahaRERA registration has lapsed. 93 units booked out of total 115 units. The concrete structure (RCC) is complete.

Read full summary

Raj Shivganga is a project by Raj Arcades & Enclaves Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800008454. It was launched in August 2017. It has 115 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2019, after an extension of 1 year from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.

93 units booked out of total 115 units (81%).