by Crescent Amity Realtors PvtLtd · Malad West, Mumbai 400064 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 3 yrs
Concrete structure
97%Mid-construction
Booked
143 of 16686% · 141 in Jul 2026
Buildings
21.3 acres
MahaRERA complaints
13Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
4
2 BHK
84
4 BHK
78
Total units
166
Buildings
2
Land
1.3 acres
Phases
1
MahaRERA complaints
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)97%
Finishes, lifts and services88%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 96%Dec 2025: Concrete structure (RCC) 97%Jul 2026: Concrete structure (RCC) 97%Oct 2026: Concrete structure (RCC) 97%Dec 2024: Final finishes 13%Dec 2025: Final finishes 55%Jul 2026: Final finishes 88%Oct 2026: Final finishes 88%Excavation 100%Concrete structure (RCC) 97%Final finishes 88%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%97%88%143
100%97%88%141
100%97%55%143
100%96%13%141

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 4 mths6 yrs 4 mths
Possession date extendedBy 3 yrs3 of 6
Possession date (MahaRERA)Dec 2026Nov 2026
Concrete structure (RCC)97%12%
Units booked86%58%
MahaRERA complaints (filed by or against the builder)139

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Centrico by Crescent Amity Realtors PvtLtd is a 166-unit SRA-sanctioned project in Malad West, Mumbai 400064, launched in August 2017 with possession due in December 2026. 143 units booked out of total 166 units. The concrete structure (RCC) is 97% complete.

Read full summary

Centrico is an SRA-sanctioned project by Crescent Amity Realtors PvtLtd in Malad West, Mumbai 400064, registered with MahaRERA as P51800008480. It was launched in August 2017. It has 166 units in 2 buildings, with 1, 2 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 3 years from the original December 2023. Construction: excavation complete, structure (RCC) 97% complete, final finishes 88% complete.

143 units booked out of total 166 units (86%). Since the July 2026 update, 2 more units have been booked and the possession date has moved from December 2024 to December 2026.