Linkpark, Malad West

by Adarsh Industrial Estate Private Limited · Malad West, Mumbai 400064 · Map

Launched
Aug 20179 yrs 2 mths promised
Possession (MahaRERA)
Oct 2026Not extended
Concrete structure
0%Early stage
Booked
182 of 32456%
Buildings
11.1 acres
MahaRERA complaints
35Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
324
Total units
324
Buildings
1
Land
1.1 acres
Phases
1
MahaRERA complaints
35

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation35%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 35%Dec 2025: Excavation 35%Jul 2026: Excavation 35%Oct 2026: Excavation 35%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 35%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
35%0%0%182
35%0%0%–
35%0%0%–
35%0%0%182

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)9 yrs 2 mths6 yrs 4 mths
Possession date extendedNo5 of 6
Possession date (MahaRERA)Oct 2026Nov 2026
Concrete structure (RCC)0%80%
Units booked56%77%
MahaRERA complaints (filed by or against the builder)3510

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Linkpark by Adarsh Industrial Estate Private Limited is a 324-unit project in Malad West, Mumbai 400064, launched in August 2017 with possession due in October 2026. 182 units booked out of total 324 units. Work on the concrete structure (RCC) has not started.

Read full summary

Linkpark is a project by Adarsh Industrial Estate Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800005832. It was launched in August 2017. It has 324 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2026, unchanged since launch. Construction: excavation 35% complete, structure (RCC) not started, final finishes not started.

182 units booked out of total 324 units (56%).