Heritage Ahura Residency, Ghatkopar West

by Kersi Jamshed Randeria · Ghatkopar West, Mumbai 400086 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2029Extended by 6 yrs 4 mths
Concrete structure
52%Mid-construction
Booked (free sale)
22 of 11918% · 132 rehab units
Buildings
51.8 acres
MahaRERA complaints
8Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale22 booked out of 119 units

Rehab132 units for existing members

Total 251 units. Rehab units are not for sale.

Project facts

1 RK
116
1 BHK
1
2 BHK
69
3 BHK
43
Other units
22
Total units
251
Buildings
5
Land
1.8 acres
Phases
1
MahaRERA complaints
8
Free-sale units
119
Rehab units
132
Reserved units
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)52%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 37%Dec 2025: Concrete structure (RCC) 37%Jul 2026: Concrete structure (RCC) 52%Oct 2026: Concrete structure (RCC) 52%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 40%Oct 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 52%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%52%40%22
100%52%40%22
100%37%0%22
100%37%0%28

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400086

Projects with 100–500 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400086
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths2 yrs 6 mths
Possession date extendedBy 6 yrs 4 mths4 of 4
Possession date (MahaRERA)Apr 2029May 2025
Concrete structure (RCC)52%96%
Units booked (free sale)18%80%
MahaRERA complaints (filed by or against the builder)81

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Heritage Ahura Residency by Kersi Jamshed Randeria is a 251-unit SRA-sanctioned project in Ghatkopar West, Mumbai 400086, launched in August 2017 with possession due in April 2029. 22 units booked out of 119 units for sale. The concrete structure (RCC) is 52% complete.

Read full summary

Heritage Ahura Residency is an SRA-sanctioned project by Kersi Jamshed Randeria in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800009207. It was launched in August 2017. It has 251 units in 5 buildings: 229 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 251 units, 119 are for sale and 132 are rehab units for existing members.

Its registered possession date is April 2029, extended by 6 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) 52% complete, final finishes 40% complete.

22 units booked out of 119 units for sale (18%).