Integrated Arya, Ghatkopar West
by Integrated Spaces Limited · Ghatkopar West, Mumbai 400086 · Map
- Launched
- Aug 20171 yr 7 mths originally promised
- Possession (MahaRERA)
- Mar 2022Extended by 3 yrs
- Concrete structure
- 88%Mid-construction
- Booked (free sale)
- 82 of 10280% · 65 rehab units
- Buildings
- 10.8 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale82 booked out of 102 units
Rehab65 units for existing members
Total 167 units. Rehab units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 125
- 2 BHK
- 31
- Other units
- 8
- Total units
- 167
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 102
- Rehab units
- 65
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 88% | 92% | 82 | |
| 100% | 88% | 92% | 82 | |
| 100% | 88% | 92% | 53 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400086
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 7 mths | 3 yrs 10 mths |
| Possession date extended | By 3 yrs | 5 of 6 |
| Possession date (MahaRERA) | Mar 2022 | Sep 2025 |
| Concrete structure (RCC) | 88% | 89% |
| Units booked (free sale) | 80% | 54% |
| MahaRERA complaints (filed by or against the builder) | 1 | 2 |
The 6 projects
- Tivon Park, Ghatkopar West
- Ashok Odyssey, Ghatkopar West
- Shree Shambhav Darshan, Ghatkopar West
- Heritage Ahura Residency, Ghatkopar West
- Skyline viha Wing B, Ghatkopar West
- Arihant Heights, Ghatkopar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Tivon Park | August 2017 | Jun 2022 – Apr 2027 | 100% | 126 units booked out of total 126 units |
| Ashok Odyssey | August 2017 | Apr 2028 | 92% | – |
| Shree Shambhav Darshan | August 2017 | December 2021 | 50% | – |
| Heritage Ahura Residency | August 2017 | April 2029 | 52% | 22 units booked out of 119 units for sale |
| Skyline viha Wing B | August 2017 | June 2024 | 86% | 48 units booked out of total 76 units |
| Arihant Heights | January 2018 | December 2026 | 100% | 47 units booked out of total 104 units |
About this project
Integrated Arya by Integrated Spaces Limited is a 167-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in August 2017 with possession due in March 2022. 82 units booked out of 102 units for sale. The concrete structure (RCC) is 88% complete.
Read full summary
Integrated Arya is a BMC-sanctioned project by Integrated Spaces Limited in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800004521. It was launched in August 2017. It has 167 units in 1 building: 159 homes (1 RK, 1 BHK and 2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 167 units, 102 are for sale and 65 are rehab units for existing members.
Possession was due in March 2022, after an extension of 3 years from the original March 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 88% complete, final finishes 92% complete.
82 units booked out of 102 units for sale (80%).