Shreeyog Chsl, Borivali West

Lapsed

by Kosmos Developers · Borivali West, Mumbai 400092 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
24%Mid-construction
Booked
–
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
18
2 BHK
25
3 BHK
1
Total units
44
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)24%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 24%Dec 2025: Concrete structure (RCC) 24%Jul 2026: Concrete structure (RCC) 24%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 24%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%24%0%–
100%24%0%–
100%24%0%44

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths5 yrs 8 mths
Possession date extendedBy 1 yr6 of 6
Possession date (MahaRERA)Dec 2020Jun 2028
Concrete structure (RCC)24%25%
Units booked–49%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shreeyog Chsl by Kosmos Developers is a 44-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 24% complete.

Read full summary

Shreeyog Chsl is an SRA-sanctioned project by Kosmos Developers in Borivali West, Mumbai 400092, registered with MahaRERA as P51800009351. It was launched in August 2017. It has 44 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2020, after an extension of 1 year from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 24% complete, final finishes not started.