Hari Smruti Chs, Borivali West

Lapsed

by Ramniyati Aditya Developers LLP · Borivali West, Mumbai 400092 · Map

Launched
Aug 20175 yrs originally promised
Possession (MahaRERA)
Dec 2024Extended by 2 yrs 4 mthsWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked (free sale)
47 of 6473% · 40 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale47 booked out of 64 units

Rehab40 units for existing members

Total 104 units. Rehab units are not for sale.

Project facts

1 BHK
16
2 BHK
33
3 BHK
17
Other units
38
Total units
104
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
64
Rehab units
40

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Dec 2024: Concrete structure (RCC) 82%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 50%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 0%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%47
0%0%0%47
100%82%50%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs4 yrs 4 mths
Possession date extendedBy 2 yrs 4 mths6 of 6
Possession date (MahaRERA)Dec 2024Mar 2027
Concrete structure (RCC)0%68%
Units booked (free sale)73%49%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Hari Smruti Chs by Ramniyati Aditya Developers LLP is a 104-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in August 2017; its MahaRERA registration has lapsed. 47 units booked out of 64 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Hari Smruti Chs is an SRA-sanctioned project by Ramniyati Aditya Developers LLP in Borivali West, Mumbai 400092, registered with MahaRERA as P51800010736. It was launched in August 2017. It has 104 units in 1 building: 66 homes (1, 2 and 3 BHK) and 38 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 104 units, 64 are for sale and 40 are rehab units for existing members.

Possession was due in December 2024, after an extension of 2 years 4 months from the original August 2022. That date has passed and no further extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.

47 units booked out of 64 units for sale (73%).