Jay Krishna, Bhandup West
by Shreegoandevi Enterprises Private Limited · Bhandup West, Mumbai 400078 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 4 yrs
- Concrete structure
- 98%Mid-construction
- Booked (free sale)
- 93 of 10787% · 88 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale93 booked out of 107 units
Rehab88 units for existing members
Land-owner share5 units, not for sale
Total 200 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 142
- 2 BHK
- 20
- Other units
- 38
- Total units
- 200
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 107
- Rehab units
- 88
- Land-owner share (not for sale)
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 93% | 98% | 60% | 93 | |
| 93% | 86% | 55% | 87 | |
| 93% | 86% | 55% | – | |
| 93% | 83% | 55% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400078
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 4 yrs 10 mths |
| Possession date extended | By 4 yrs | 4 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Jan 2026 |
| Concrete structure (RCC) | 98% | 55% |
| Units booked (free sale) | 87% | 59% |
| MahaRERA complaints (filed by or against the builder) | 1 | 2 |
The 6 projects
- Samriddhi Garden Wing C Gulmohar Wing D Deodhar, Bhandup West
- Sudhanshu Imperia, Bhandup West
- Marathon Neosquare A, Bhandup West
- Sunshine Oakwood, Bhandup West
- Vastukalp, Bhandup West
- Dp Star Trinetra, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Samriddhi Garden Wing C Gulmohar Wing D Deodhar | August 2017 | December 2026 | 100% | 139 units booked out of total 173 units |
| Sudhanshu Imperia | August 2017 | Mar 2026 | 100% | – |
| Marathon Neosquare A | August 2017 | April 2027 | 100% | 136 units booked out of total 150 units |
| Sunshine Oakwood | August 2017 | March 2024 | 0% | 15 units booked out of total 236 units |
| Vastukalp | August 2017 | December 2025 | 10% | 89 units booked out of total 238 units |
| Dp Star Trinetra | August 2017 | December 2024 | 8% | – |
About this project
Jay Krishna by Shreegoandevi Enterprises Private Limited is a 200-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in August 2017 with possession due in December 2027. 93 units booked out of 107 units for sale. The concrete structure (RCC) is 98% complete.
Read full summary
Jay Krishna is an SRA-sanctioned project by Shreegoandevi Enterprises Private Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800010788. It was launched in August 2017. It has 200 units in 1 building: 162 homes (1 and 2 BHK) and 38 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 200 units, 107 are for sale, 88 are rehab units for existing members and 5 are the land-owner's share, not for sale.
Its registered possession date is December 2027, extended by 4 years from the original December 2023. Construction: excavation 93% complete, structure (RCC) 98% complete, final finishes 60% complete.
93 units booked out of 107 units for sale (87%). Since the July 2026 update, 6 more units have been booked, the reported concrete structure (RCC) has gone from 86% to 98% and the possession date has moved from December 2024 to December 2027.