Sudhanshu Imperia, Bhandup West
Ready to moveLapsed
by Sudhanshu Infrastructures Private Limited · Bhandup West, Mumbai 400078 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Mar 2026Extended in both phasesWhat does Lapsed mean?
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 28
- 1 BHK
- 103
- 2 BHK
- 20
- Other units
- 6
- Total units
- 157
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 2
- MahaRERA complaints
- 0
- Reserved units
- 12
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Sudhanshu Imperia Completed | P51800003303 | 86 | 100% | – | |
| Sudhanshu Imperia Wing C Ready to move Lapsed | P51800027547 | 65 | 100% | 100% |
Show updates by phase
Sudhanshu Imperia (P51800003303)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 74 |
"–" means MahaRERA shows no figure for that update.
Sudhanshu Imperia Wing C (P51800027547)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 70 | |
| 100% | 100% | 0% | 70 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 57 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400078
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 6 mths | 5 yrs 10 mths |
| Possession date extended | Yes | 5 of 6 |
| Possession date (MahaRERA) | Mar 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 99% |
| Units booked | – | 80% |
| MahaRERA complaints (filed by or against the builder) | 0 | 2 |
The 6 projects
- Marathon Neosquare A, Bhandup West
- Jay Krishna, Bhandup West
- Samriddhi Garden Wing C Gulmohar Wing D Deodhar, Bhandup West
- Sunshine Oakwood, Bhandup West
- Dp Star Trinetra, Bhandup West
- Skicity Phase 1, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Marathon Neosquare A | August 2017 | April 2027 | 100% | 136 units booked out of total 150 units |
| Jay Krishna | August 2017 | December 2027 | 98% | 93 units booked out of 107 units for sale |
| Samriddhi Garden Wing C Gulmohar Wing D Deodhar | August 2017 | December 2026 | 100% | 139 units booked out of total 173 units |
| Sunshine Oakwood | August 2017 | March 2024 | 0% | 15 units booked out of total 236 units |
| Dp Star Trinetra | August 2017 | December 2024 | 8% | – |
| Skicity Phase 1 | August 2017 | December 2026 | 100% | 93 units booked out of total 162 units |
About this project
Sudhanshu Imperia by Sudhanshu Infrastructures Private Limited is a 157-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, registered with MahaRERA in 2 phases, with possession due in March 2026. The concrete structure (RCC) is complete.
Read full summary
Sudhanshu Imperia is an SRA-sanctioned project by Sudhanshu Infrastructures Private Limited in Bhandup West, Mumbai 400078, registered with MahaRERA as 2 phases (P51800003303, P51800027547). The first phase was launched in August 2017. Together the phases have 157 units in 2 buildings: 151 homes (1 RK, 1 BHK and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is lapsed.
The registered possession date is March 2026; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 98% complete. Both phases have their structure complete.