Marathon Neosquare A, Bhandup West
Ready to move
by Marathon Nextgen Realty Ltd · Bhandup West, Mumbai 400078 · Map
- Launched
- Aug 20175 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 4 yrs 4 mths
- Concrete structure
- 100%Ready to move
- Booked
- 136 of 15091%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 50
- 1 BHK
- 82
- 2 BHK
- 18
- Total units
- 150
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 92% | 136 | |
| 100% | 100% | 92% | – | |
| 100% | 100% | 92% | – | |
| 100% | 100% | 57% | 136 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400078
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 5 yrs 4 mths |
| Possession date extended | By 4 yrs 4 mths | 5 of 6 |
| Possession date (MahaRERA) | Apr 2027 | Jul 2026 |
| Concrete structure (RCC) | 100% | 99% |
| Units booked | 91% | 69% |
| MahaRERA complaints (filed by or against the builder) | 5 | 0 |
The 6 projects
- Sudhanshu Imperia, Bhandup West
- Jay Krishna, Bhandup West
- Samriddhi Garden Wing C Gulmohar Wing D Deodhar, Bhandup West
- Sunshine Oakwood, Bhandup West
- Dp Star Trinetra, Bhandup West
- Skicity Phase 1, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sudhanshu Imperia | August 2017 | Mar 2026 | 100% | – |
| Jay Krishna | August 2017 | December 2027 | 98% | 93 units booked out of 107 units for sale |
| Samriddhi Garden Wing C Gulmohar Wing D Deodhar | August 2017 | December 2026 | 100% | 139 units booked out of total 173 units |
| Sunshine Oakwood | August 2017 | March 2024 | 0% | 15 units booked out of total 236 units |
| Dp Star Trinetra | August 2017 | December 2024 | 8% | – |
| Skicity Phase 1 | August 2017 | December 2026 | 100% | 93 units booked out of total 162 units |
About this project
Marathon Neosquare A by Marathon Nextgen Realty Ltd is a 150-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in August 2017 with possession due in April 2027. 136 units booked out of total 150 units. The concrete structure (RCC) is complete.
Read full summary
Marathon Neosquare A is a BMC-sanctioned project by Marathon Nextgen Realty Ltd in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800010386. It was launched in August 2017. It has 150 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 4 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes 92% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
136 units booked out of total 150 units (91%).
Marathon's track record in Mumbai
MahaRERA projects registered 2017–2024 in Mumbai
| Projects registered with MahaRERA | 11 |
|---|---|
| Total units across these projects | 818 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 2 |
| Lapsed | 6 |
| Under construction | 3 |
| Possession date extended on the builder's application | 5 |
| Typical time from launch to 100% structure | 4 years 6 months |
| MahaRERA complaints (filed by or against the builder), all Marathon projects | 11 (5 of 11 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.