Sheetal Tapovan, Malad East

by Dgs Township Pvt Ltd · Malad East, Mumbai 400097 · Map

Launched
Aug 20175 yrs 10 mths originally promised
Possession (MahaRERA)
May 2024Extended by 11 mths
Concrete structure
100%Nearing possession
Booked
264 of 27397%
Buildings
11.1 acres
MahaRERA complaints
13Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
7
1 BHK
233
2 BHK
20
3 BHK
9
4 BHK
1
Other units
3
Total units
273
Buildings
1
Land
1.1 acres
Phases
1
MahaRERA complaints
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 50%Dec 2025: Final finishes 70%Jul 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 100%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%264
100%100%70%264
100%85%50%213

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400097

Projects with 100–600 flats, launched within 1 year of this one.

Compared with 5 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 10 mths5 yrs 9 mths
Possession date extendedBy 11 mths5 of 5
Possession date (MahaRERA)May 2024Jul 2024
Concrete structure (RCC)100%75%
Units booked97%88%
MahaRERA complaints (filed by or against the builder)1319

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Sheetal Tapovan by Dgs Township Pvt Ltd is a 273-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in August 2017 with possession due in May 2024. 264 units booked out of total 273 units. The concrete structure (RCC) is complete.

Read full summary

Sheetal Tapovan is a BMC-sanctioned project by Dgs Township Pvt Ltd in Malad East, Mumbai 400097, registered with MahaRERA as P51800011437. It was launched in August 2017. It has 273 units in 1 building: 270 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in May 2024, after an extension of 11 months from the original June 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.

264 units booked out of total 273 units (97%).